Precedence requirements, assembly line

1. Precedence requirements specify

A.the cycle time and flow time requirements
B.the physical restrictions on the order in which operations are performed
C.the bottleneck and output objectives
D.the efficiency and balance delay

2. With a ___________ layout activities arranged in a line according to the sequence of operations.

A.process
B.product
C.fixed-position
D.cellular

3. An assembly line manufacturing company hopes to achieve a daily output of 200 units during 6 hours of production time, the desired cycle time to achieve the targeted level of output is

a) 3.0 minutes
b) 1.8 minutes
c) 1.5 minutes
d) 0.03 minutes